Water Fund reserves for HMI remediation street and stormwater work
A 2018 water main leak on the HMI property left the city on the hook for repairs. This $921,500 from water reserves covers the street and stormwater portion — but slope stabilization down into the canyon and retaining walls are still being designed, with more costs to come.
Future of curbside recycling
A citizen survey found 85% of 1,200+ respondents would support recycling if plastics #1 and #2 were accepted and the price dropped; 69% wouldn't give it up even for $5.79/month savings. Top complaint: too few accepted materials. Council decides next week.
PFAS contamination at the Airport well
PFAS 'forever chemicals' were found at the Airport well, and the EPA set strict new limits in 2024. The city is using a $4.86M state grant to drill new wells (a driller is already on site) or install filtration if needed. Long-term exposure is the concern, not immediate health risk.
Water system maintenance vac truck purchase
The city is buying a $665,034.50 combination vacuum/water truck to replace a 2013 unit. It digs precise holes with high-pressure water for water line and meter repairs — less street damage, less shoveling, faster leak fixes.
Canyon Rim Drop Line sewer project design
The main sewer trunk line carrying about half the city's wastewater down the canyon rim is 30 years old and can't be bypass-pumped if it fails. The council funded final design of a new route along a safer alignment so bidding can start next.
South Well #5 and Pheasant PRV water projects
A change order merges the new Pheasant Road pressure zone work into the South Well #5 project, saving money and time on water system improvements.
Wastewater treatment plant air line replacement
The dewatering building's HVAC unit is corroding from hydrogen sulfide gas and humidity, and a headworks unit just failed. The council tapped wastewater reserves to finish these projects before fiscal year end.
Canyon Springs Pump Station investigation
The corridor is a critical link between the city's water supply north of the Snake River and Harrison Tank. The study will help determine whether the city should ask voters to fund infrastructure investment, possibly through a bond. The old authorization expired September 30, 2025.
Rock Creek sewer line completion
A $57,000 change order fixes soil that never revegetated on a private property along the sewer line near Addison — new topsoil, reseeding and fencing to keep horses off.
Harrison Booster Station HVAC replacement
Two new HVAC units for the Harrison Booster Station, paid from $65,000 in water reserves.
Lease of water shares to Southwest Irrigation District
In a short water year, the city will lease 500 water shares to the Southwest Irrigation District so area farmland isn't fallowed — half the usual amount, capped to protect the city's own pressurized irrigation users.
Wastewater plant contract overages
Wastewater reserves will absorb $51,414 in cost overruns from last fiscal year's treatment plant and lift station operations contract.